Renovations to The Shores At Spooners Creek January 2016
Since original construction of The Shores in 2006 there had been problems with mildew and rain water leaks. To address the issues, The Shores HOA Board hired a company staffed by architects, engineers and experts in construction to investigate and determine the exact causes. They found two major causes: 1) Air Penetration 2) Water Intrusion. With the problems clearly identified and found to be the result of improper construction the Board moved forward with obtaining compensation to repair the problems. Following a lengthy litigation with the original general contractor and some of their sub-contractors, a settlement was reached.
The HOA then contracted with Stancil Builders to perform the repairs under the watchful direction of the engineering / architectural firm of Fuller Group Inc. from South Carolina and the renovations to the buildings were begun in January of 2016.
The photo album below is a compilation of photos taken during the repairs to The Shores. You will see that Water Intrusion into several condos was eliminated by removing poorly installed exterior siding and flashings. Air Intrusion of all the condos was eliminated by removing the existing insulation in the inside exterior facing walls and replacing it with open cell foam (sprayed application) as well as the sealing of numerous "holes" found in the exterior walls which allowed warm moist air to flow into the condos . The two problems which were determined by the engineers and architects were thus eliminated.
(revised 4/4/16)
(Click on any photograph to enlarge)